Chemical Industry and Engineering Progress ›› 2018, Vol. 37 ›› Issue (11): 4451-4459.DOI: 10.16085/j.issn.1000-6613.2018-0210

Previous Articles     Next Articles

Evaluation on technology of desulfurization wastewater from coal-fired power plant based on fuzzy AHP

MA Shuangchen1, FAN Zixuan1, WEN Jiaqi1, MA Lan1, ZHAO Baohua2, ZHANG Jinzhu2, SUN Yao1   

  1. 1 College of Environmental Science and Engineering, North China Electric Power University, Baoding 071003, Hebei, China;
    2 Huadian Zhengzhou Machinery Design Research Institute Co., Ltd., Zhengzhou 450046, Henan, China
  • Received:2018-01-23 Revised:2018-07-19 Online:2018-11-05 Published:2018-11-05

基于模糊层次分析的燃煤电厂脱硫废水处理可利用技术评价

马双忱1, 范紫瑄1, 温佳琪1, 马岚1, 赵保华2, 张金柱2, 孙尧1   

  1. 1 华北电力大学环境科学与工程系, 河北 保定 071003;
    2 华电郑州机械设计研究院有限公司, 河南 郑州 450046
  • 通讯作者: 马双忱(1968-),男,教授,博士生导师。E-mail:msc1225@163.com。
  • 作者简介:马双忱(1968-),男,教授,博士生导师。E-mail:msc1225@163.com。
  • 基金资助:
    国家重点研发计划(2018YFB0604305)及中央高校基金(2016XS115)项目。

Abstract: To 2015 years or so, the control of atmospheric pollutants in China's power industry has been rectified with the latest atmospheric control requirements, and the focus of environmental management has gradually turned to water pollution prevention and control. The whole plant water treatment of coal-fired power plant includes pollutant removal, water resource reuse, reducing water intake and drainage, problems in this area began to rise as major environmental problems. The desulfurization wastewater of coal-fired power plant is the whole plant terminal wastewater, its suspended substance, chemical oxygen demand, heavy metal and inorganic salt pollutant have high concentration, which is harmful to the environment. In this paper, according to the fuzzy analytic hierarchy process(FAHP) model in the evaluation of engineering technical scheme, the different desulfurization wastewater treatment technologies were modeled. The influencing factors were selected and the model was calculated. The comprehensive sequencing of several desulfurization wastewater treatment technologies and the best available technology were obtained. It can provide a reference for the scheme selection of the desulfurization wastewater treatment in coal-fired power plant.

Key words: coal power plant, desulfurization wastewater, treatment technology, fuzzy comprehensive evaluation

摘要: 至2015年左右,我国电力行业的大气污染物控制已经随着最新大气控制要求整治完毕,环境治理重点开始逐步转向水污染防控。燃煤电厂全厂水处理包括水污染物去除、水资源回用、减少取水和排水,该领域问题开始上升为主要的环境难题。燃煤电厂脱硫废水是全厂终端废水,其悬浮物、化学需氧量、重金属、无机盐污染物浓度高,对环境危害大。本文根据工程技术方案评价中常用的模糊层次分析(FAHP)模型,对不同的脱硫废水处理技术进行了详细的建模、影响因素选取及模型计算过程研究,得出了几种参评脱硫废水处理技术的优劣综合排序以及最佳可利用技术,以期对燃煤电厂脱硫废水深度处理的方案选择提供参考。

关键词: 燃煤电厂, 脱硫废水, 废水处理技术, 模糊综合评价