化工进展 ›› 2017, Vol. 36 ›› Issue (04): 1231-1239.DOI: 10.16085/j.issn.1000-6613.2017.04.011

• 化工过程与装备 • 上一篇    下一篇

夹点技术优化改造蜡油加氢裂化装置换热网络及有效能分析

李中华1, 肖武1, 贺高红1, 杜艳泽2, 方向晨2, 罗立3   

  1. 1 大连理工大学精细化工国家重点实验室, 膜科学与技术研究开发中心, 辽宁 大连 116024;
    2 中国石化抚顺石油化工研究院, 辽宁 抚顺 113001;
    3 北京沃利帕森工程技术有限公司, 北京 100015
  • 收稿日期:2016-10-08 修回日期:2016-11-03 出版日期:2017-04-05 发布日期:2017-04-05
  • 通讯作者: 肖武,博士,副教授,从事化学工程、化工系统工程及过程强化等方面研究。E-mail:wuxiao@dlut.edu.cn。
  • 作者简介:李中华(1991-),女,硕士研究生。
  • 基金资助:
    中国石油化工股份有限公司(X514001)、国家留学基金(201506060258)、长江学者奖励计划(T2012049)、辽宁省高等学校创新团队(LT2015007)及中央高校基本科研业务费专项基金(DUT16TD19)项目。

Optimization and reformation of heat exchanger network for wax oil hydrocracking unit by pinch technology and exergy analysis

LI Zhonghua1, XIAO Wu1, HE Gaohong1, DU Yanze2, FANG Xiangchen2, LUO Li3   

  1. 1 State Key Laboratory of Fine Chemicals R & D Center of Membrane Science and Technology, Dalian University of Technology, Dalian 116024, Liaoning, China;
    2 Fushun Research Institute of Petroleum and Petrochemicals, Fushun 113001, Liaoning, China;
    3 Beijing Worley Parsons Engineering Technology Co., Ltd., Beijing 100015, China
  • Received:2016-10-08 Revised:2016-11-03 Online:2017-04-05 Published:2017-04-05

摘要: 针对某炼厂150万吨蜡油加氢裂化装置,采用单段串联+冷高分+常压塔+减压塔+轻烃吸收塔工艺流程,基于生产数据利用Aspen Plus软件对装置中反应部分和分离部分的各个单元模块进行模拟,通过参数的调整,使得模拟结果与标定数据达到很好的吻合,进而获得各个流股的热力学参数。结合夹点技术对其换热网络进行能效分析,进而找到该工艺流程中的用能“瓶颈”,在不改变装置主要设备的前提下,对现有换热网络调优并模拟计算得到节能方案,同时利用有效能分析方法对改造前后换热网络进行用能评价。调优后,热公用工程用量为25709kW,相比原工艺流程节约了42.20%,冷公用工程用量为29863kW,相比原工艺流程节约了38.50%;总体来看改造方案相比原工艺流程节约了17.19kgEO/t的能耗。换热网络的总(火用)损失也由原来的13530kW降低到8477kW,总(火用)损失降低了37.35%。

关键词: 加氢裂化, 有效能分析, 换热网络, 夹点技术

Abstract: A wax oil hydrocracking process unit with annual capacity of 1.5 million tons in a refinery was simulated using Aspen Plus. The unit included single segment series,cold high pressure column,and light hydrocarbon absorber vacuum tower. Based on the basic production data of wax oil hydrocracking units,Aspen Plus software was used to establish a strict mathematical model for each module in the process. By adjusting the model parameters,the simulation results and calibration data were in a good agreement. Then thermodynamic parameters of different streams were obtained from the simulation. Based on the simulation,the "bottleneck" of the heat exchanger network for the process was identified using pinch analysis.,With the premise of not changing the main equipment of the system,the tuning and simulation of the existing heat exchanger network were achieved for the energy-saving program. The effective energy analysis method was also used to evaluate the heat exchange network before and after the reformation. After the tuning,the amount of hot utility was the 25709kW that is 42.2% less than original process;the amount of cold utility was 29863kW that was 38.5% less than the original process. Overall,the transformation program would save energy 17.19kgEO/t total exergy loss of the heat exchanger network would be reduced to 8477kW from 13530kW with the total exergy loss decreased by 37.35%.

Key words: hydrocracking, exergy analysis, heat exchanger network, pinch technology

中图分类号: 

京ICP备12046843号-2;京公网安备 11010102001994号
版权所有 © 《化工进展》编辑部
地址:北京市东城区青年湖南街13号 邮编:100011
电子信箱:hgjz@cip.com.cn
本系统由北京玛格泰克科技发展有限公司设计开发 技术支持:support@magtech.com.cn